Fosterville Gold Mine FGM – Samplers Upgrade

Mincore has completed the Design, Supply, Construct and Commissioning of automatic samplers into 7 locations around the process plant mainly are Cyclone Overflow, Flotation Tails, Neutralisation Tails, BIOX FeeCyanide Destruct Tails, CIL Tails and Flash Flotation Concentrate.

Fosterville Gold Mine FGM – Samplers Upgrade

Mincore assisted FGM by delivering fast tracked design, procurement and construction services, including:

  • Front end and detailed engineering of the long lead items.
  • Client 15%, 30% and 70% Design Reviews to lock down design with end-user at an early stage
  • Consideration to surrounding installations tie-ins.
  • Underground & aboveground piping.
  • Multiple work-fronts opened at the same time in strict accordance with safest methodologies
  • Off-site pre-assembly at Vendor’s workshop optimised
  • Hazop performed and actions